 Waterline Replacement
Hillsboro, Illinois
Prepared plans and specifications and construction observation for
installation of approximately 30,000 lineal feet of 8-inch to 12-inch
water mains to replace 2-inch and 4-inch waterlines, and to provide
feeder lines for additional fire flows.
Waterline Replacement
Schram City, Illinois
Prepared plans, specifications and performed construction observation
for replacement of approximately 3,500 lineal feet of 2-inch waterline
with 6-inch waterline.
Sauget Industrial Park
Sauget, Illinois
Prepared plans and specifications for approximately 6,000 lineal feet of
12-inch waterline for new industrial park near Bi-State Airiport.
Pinnacle Point Subdivision
Glenn Shoals Lake
Hillsboro, Illinois
Prepared plans and specifications for approximately 20,000 lineal feet of
6-inch water main to serve new subdivision.
Illinois Route 127 Water Line Extension
Greenville, Illinois
Hurst-Rosche Engineers, Inc. is providing all standard engineering
services for extension of an eight-inch water main south along Illinois
Route 127 to a point just south of Greenville Airport, including project
design, surveying, specifications, bidding supervision and bid
recommendations, and engineering/ construction supervision.
White Subdivision
Hillsboro, Illinois
Prepared plans and specifications for approximately 5,000 lineal feet of
6-inch water main in new subdivision.
Water Survey
Commonfields of Cahokia, Illinois
Hurst-Rosche is currently preparing plans and specifications for the
construction of a 24-inch waterline to supply treated water to the
District from the St. Louis City water supply. The 24-inch water line
will be placed under the Mississippi River by directional boring methods.
ADGPTV Water Commission
Treatment Systems Evaluation and Capital Improvement Feasibility Study
Study all treatment processes including raw water supply (impoundment) for
treatment extensions, increased capacity, upgrade potential and related
costs. The distribution system was also reviewed in terms of conveyance
limits, pumping and telemetry controls. A three million dollar capital program
was initiated as a result of this study as well as a treatment plant
increased capacity rating by EPA.
ADGPTV Water Commission
Water Transmission Main and 1,000,000 Gallon Elevated Water Storage Tank
Design and construction administration of a nine mile 16” diameter water
transmission main. The project also included a 1 million gallon elevated water
storage tank constructed of reinforced concrete and steel. Computer
aided hydraulic analysis were performed to verify tank and line sizing. All
surveying easement plats and staking were also performed by Hurst-Rosche
Engineers, Inc.
Well Supply and Distribution System
Raymond, Illinois
Raymond, a village of 950, receives water from a well supply. Hurst-Rosche
has designed the wells, studied hydrology, and studied alternatives for new
well locations all for the purpose of developing an additional municipal
water supply resource. Hurst-Rosche has also been involved with well water
treatment in Raymond with sequestration being the primary process used.
Hurst-Rosche has designed several projects to extend 6-inch mains into new
subdivisions and to serve commercial development.
|